The painting of the exterior hallways of the building are about to start in building 8105. Below is the schedule weather permitting:
Friday April 9th, 2021 – all cracks will be cut and urethane will be applied in all areas that require this application, on all four (4) floors.
Monday April 12th, 2020 – Texture will be applied to all urethane areas, on all four (4) floors.
Tuesday April 13th, 2021 – Macro Poxy will be applied to the first and second floors. The elevator may be down for periods of time on those floors while work is be performed.
Wednesday April 14th, 2021 – The first coat of waterproofing paint will be applied to the first and second floors. The elevator may be down for periods of time on those floors while work is be performed.
Thursday April 15th, 2021 - The second coat of waterproofing paint will be applied to the first and second floors. The elevator may be down for periods of time on those floors while work is be performed.
Friday April 16th, 2021 – The final clear coat application will be applied to the first and second floors. The elevator may be down for periods of time on those floors while work is be performed.
Monday April 19th, 2021 – Macro Poxy will be applied to the third and fourth floors. The elevator may be down for periods of time on those floors while work is be performed.
Tuesday April 20th, 2021 – The first coat of waterproofing paint will be applied to the third and fourth floors. The elevator may be down for periods of time on those floors while work is be performed.
Wednesday April 21st, 2021 - The second coat of waterproofing paint will be applied to the third and fourth floors. The elevator may be down for periods of time on those floors while work is be performed.
Thursday April 22nd, 2021 – The final clear coat application will be applied to the third and fourth floors. The elevator may be down for periods of time on those floors while work is be performed.
Please keep in mind that this area of the painting is the most challenging for the painters and members in regard to movement around the building, there will be some building mobility inconveniences during this phase. Also, weather conditions may adjust this schedule.